Description
A comment was made on the wiki:
If you have two events in particular month in calendar, let say one from the current month and second from the continuation of previous month, then the first one is disapearing. if there is only one event. then it works fine. however, it doesn't show event if the there are two one is from last month
If you have two events in particular month in calendar, let say one from the current month and second from the continuation of previous month, then the first one is disapearing. if there is only one event. then it works fine. however, it doesn't show event if the there are two one is from last month
Activity
Brad Kroeger
created issue -
Brad Kroeger
made changes -
Field | Original Value | New Value |
---|---|---|
Status | Open [ 1 ] | Resolved [ 5 ] |
Fix Version/s | EE-2.0.0.Beta1 [ 10254 ] | |
Fix Version/s | 1.8.2.GA_P03 [ 10253 ] | |
Resolution | Fixed [ 1 ] | |
Assignee | Brad Kroeger [ brad.kroeger ] | Ken Fyten [ ken.fyten ] |
Brad Kroeger
made changes -
Assignee | Ken Fyten [ ken.fyten ] | Brad Kroeger [ brad.kroeger ] |
Ken Fyten
made changes -
Fix Version/s | EE-2.0.0.Alpha1 [ 10260 ] | |
Fix Version/s | EE-2.0.0.Beta1 [ 10254 ] | |
Fix Version/s | 1.8.2.GA_P03 [ 10253 ] |
Ken Fyten
made changes -
Status | Resolved [ 5 ] | Closed [ 6 ] |
Week view fixes: Multiple events running into next month now visible, can have more than one all day event starting in same day.